Settings for Sales Target Planning
If you
would like to set up Sales Target Planning independently of the
delivered example scenario, you need to make the settings described in this
section. You make some of these settings in the BW-BPS
Planning
Environment, and others using the Planning Services
belonging to CRM Analytics. To enable you to follow the steps in the system
using the example scenario, some of the steps refer to the name of the
respective object in the example scenario.
...
1.
In the
planning environment, create a
planning area for
sales planning.
The delivered example scenario uses the planning area sales planning (4CRMSP01).
2.
Create
a
planning
level for the planning area. For those characteristics that are to be used
to specify the responsibilities of the individual planners, set the Selection in Package indicator.
3.
Create
planning functions for the planning level (see
Planning
Functions, Predefined Planning
Functions, and Business Planning
Functions). Do not create any
planning packages.
Instead, use the ad hoc package. This is necessary for structuring the
worklist by responsibilities.
4.
For
manual
planning, create a
planning layout.

For more information about the procedure for
creating planning areas, planning levels, planning packages, and planning
functions, see
Setting Up the
Planning Architecture.
5.
Create
a
planning
folder under Business Planning and Simulation
® Planning Content ® CRM
Analytics
® Planning
Services ® Customizing for Planning Folders. Note the
following:
All layouts in a planning folder need to have a similar structure. This means that, whereas a layout can contain more or less characteristics than another layout, the layouts should not contain different characteristics.
The delivered example scenario uses the following planning folders:
· Global Sales Targets
· Sales Manager
· Sales Employees
6. In the planning environment for the planning area, create variables for defining worklists and assign the values to the individual planners who are responsible for those values.
7. Select the planning area under Business Planning and Simulation ® Planning Content ® CRM Analytics ® Planning Services ® Select Planning Area.
You execute automatically for this planning area all of the settings described below that you make in the transaction Settings for Planning Services.
8. Choose Business Planning and Simulation ® Planning Content ® CRM Analytics ® Planning Services ® Customizing.
9. Under Origin of the Responsibilities, select the variables that you created in step 6.
10. Specify the hierarchies for sales planning (see Specifying Hierarchies).
11. To have the correct units of measure selected flexibly and automatically for sales planning, you can make additional settings under Units of Measure (see Units of Measure Specific to Characteristic Values).
12. If you want to change the planning layout display and include additional calculated key figures, for example, enhance the planning layout accordingly (see Enhancing the Planning Layout).
13. Test the settings under Complete Test.
14. If you would like to perform sales planning from within SAP CRM, make the settings described under CRM Analytics ® Settings for Calling Up Sales Planning in SEM in the Implementation Guide for SAP CRM.
When a given planner executes sales target planning, the system first determines the planning folders. A user-specific worklist is generated for each planning folder on the basis of the settings made (see also Structuring the Worklist by Responsibilities). By selecting a task in the worklist, the corresponding planning layout is called up and the planner can enter his/her planning figures there.