Show TOC

 Account Assignment and Budgeting

Definition

The assignments of a force element to objects in Accounting, Funds Management, and Project System.

Use

To include force elements in accounting, funds management, and project system processes, you assign force elements to the relevant objects/levels:

  • Cost centers

    The assignment of a cost center forms the basis for the personnel and logistics processes for force elements.

  • Cost center groups

  • Profit centers

  • Profit center groups

  • WBS elements

  • Funds centers

As a result, lower-level force elements and positions inherit the assignments of the higher-level force element, unless an assignment has been made directly for them.

For information about editing these assignments, see Assignment of Account Assignment Objects and Budgeting Objects .

Structure

ControllingTab Page

On Controlling tab page in the Structures Workbench , the system displays (in the upper screen area) an overview of the account assignment objects assigned directly or inherited.

In the lower screen area, you can display or edit the following assignments of a force element to CO objects:

Assignments to CO objects

Relationship

Object Types

Storage

A 011

Assigned Master Cost Centers

O – K

Infotype 1001

A 003

Assigned Profit Centers

O – PC

Infotype 1001

A 015

Assigned Cost Center Groups

O – KG

Infotype 1270

A 015

Assigned Profit Center Groups

O – PH

Infotype 1270

No relationship

Inherited Master Cost Centers

O – K

For technical reasons, assignment is only simulated using the relationships 850, 851 and 852.

To choose between the different assignments, you can choose Choose Relationship . The following properties are mapped:

  • Name/ID/Code

    Assigned object

  • Assigned as of / Assigned Until

    The validity period of the assignment between the object and force element.

  • Object Status

    The status of the assigned object.

  • Valid from / Valid to

    The validity period of the assigned object.

  • Relationship Text

    A description of the relationship.

  • Relationship Status

    The status of the relationship.

    Note Note

    To show and hide fields, you can choose Column Configuration .

    End of the note.
  • For Planned Operation / Planned Delimitation Date / Status , see Delimitation/Deletion with Status Change .

By choosing Overview of Account Assignments , you can display an overview of all assignments.

Funds ManagementTab Page

On the Funds Management tab page in the Structures Workbench , you can edit and display the integration of the force element to the Funds Management component.

  • Funds Center

    The object ID of the assigned funds center.

  • Name

    The name of the assigned funds center.

  • Description

    The description of the assigned funds center.

Choose Display Funds Center to display details. Choose FM Derivation Tool to change the derivation strategy used by the system.

See also Funds Center Derivation .

Account Assignmenttab page

The following fields are available in the Structures Workbench on the Account Assignment tab page:

  • Planning Status

    The status of the assignment.

  • Controlling Area

    You assign a controlling area to a root force element.

  • Business Area

    You assign a business area to the force element.

  • Company Code

    You assign a company code to the force element.

  • Plant

    You assign a plant to the force element.

  • Personnel Area

    You assign a personnel area to the force element. A company code can cover several personnel areas.

  • Personnel Subarea

    You assign a personnel subarea to the force element. A personnel area can cover several personnel subareas.

  • For Planned Operation , see Delimiting/Deleting with Status Change .

The assignment of these account assignment characteristics to the force element is stored in infotype 1008 .

WBS Elementtab page

The following fields are available in the Structures Workbench on the WBS Element tab page for assigning WBS elements to a force element:

  • WBS element (master)

    • Project Def.

      The project definition for the assigned master WBS element.

    • WBS Element

      The object ID of the assigned master WBS element.

    • Name

      The name of the assigned master WBS element.

    • For Planned Operation / Planned Delimitation Date / Status , see Delimitation/Deletion with Status Change .

      The assignment of a WBS element to the force element is stored in table /ISDFPS/FORCE .

  • Additional WBS Element Assignments

    In addition to the master WBS element assignment, you can also assign additional WBS elements. You can use these assignments to assign mapped projects to force elements using WBS elements. The assignment of these WBS elements is stored in infotype 1001 through the relationship A 108 .

    You can call up an overview in calendar form by choosing Graphical Display (see also Calendar Display ) or using reports for the operation/exercise calendar .

Integration

The data for the master cost center is copied to the Organizational Assignment infotype (0001) in Personnel Administration .

Data for the controlling area, business area, personnel area, and personnel subarea is used as default values in Personnel Administration .