Show TOC

Function documentationPlanning Services for Realignment of Demand History

 

To ensure that the demand history reflects changes, the system adjusts the demand history when various events occur and realigns the data.

Features

The system initiates data realignment of the demand history either with triggers or you must have scheduled it as a regular service in the Planning Service Manager (PSM). For more information, see Use of the Planning Service Manager in SPP and PSM Services for Demand History Creation.

The following table provides an overview of the events for which data realignment is necessary and which planning services perform this realignment:

Event

Planning Service

Technical Name of Planning Service

Triggered by

Change to location determination procedure

SPP: Data Realignment for Loc.Det.Schema

SPP_PDEM_SERPAT_RLG

---

Stocking or destocking decision

SPP: Data Real. For Stocking/Destocking

SPP_PDEM_STOCKING_RLG

SPP_REPL_INDI_CHANGE

Change to TPOP status

SPP: Data Realignment for TPOP

SPP_PDEM_TPOP_RLG

SPP_NON_TPOP

and

SPP_TPOP

Assignment of future BOD to product

SPP: Create Demand History Future BOD

SPP_PDEM_BOD_ASSIGN

SPP_NEW_BOD_ASSIGN

Deletion of future BOD assignment

SPP: Delete Demand History Future BOD

SPP_PDEM_BOD_DELETE

SPP_BOD_DELETE

Future BOD becomes valid

SPP: Data Realignment for BOD Change

SPP_PDEM_BOD_VALID

---

Supersession

SPP: Data Realignment for Supersession

SPP_PDEM_SUPERSESSION_RLG

---

Promotion

SPP: Data Realignment for Promotion

SPP_PDEM_PROMOTION_RLG

---

Change to periods in the calendar master data

SPP: Calendar Change Realignment

SPP_PDEM_CLD_RLG

SPP_CLD_CHG

Change to final demand

SPP: Adjustment of Demand History

SPP_PDEM_OVR_RLG