Planning Services for Realignment of Demand History
To ensure that the demand history reflects changes, the system adjusts the demand history when various events occur and realigns the data.
You have made the settings for historical capture and maintenance.
You have captured the historical data.
The system initiates data realignment of the demand history either with triggers or you must have scheduled it as a regular service in the Planning Service Manager (PSM). For more information, see Use of the Planning Service Manager in SPP and PSM Services for Demand History Creation.
The following table provides an overview of the events for which data realignment is necessary and which planning services perform this realignment:
Event |
Planning Service |
Technical Name of Planning Service |
Triggered by |
Change to location determination procedure |
SPP: Data Realignment for Loc.Det.Schema |
SPP_PDEM_SERPAT_RLG |
--- |
Stocking or destocking decision |
SPP: Data Real. For Stocking/Destocking |
SPP_PDEM_STOCKING_RLG |
SPP_REPL_INDI_CHANGE |
Change to TPOP status |
SPP: Data Realignment for TPOP |
SPP_PDEM_TPOP_RLG |
SPP_NON_TPOP and SPP_TPOP |
Assignment of future BOD to product |
SPP: Create Demand History Future BOD |
SPP_PDEM_BOD_ASSIGN |
SPP_NEW_BOD_ASSIGN |
Deletion of future BOD assignment |
SPP: Delete Demand History Future BOD |
SPP_PDEM_BOD_DELETE |
SPP_BOD_DELETE |
Future BOD becomes valid |
SPP: Data Realignment for BOD Change |
SPP_PDEM_BOD_VALID |
--- |
Supersession |
SPP: Data Realignment for Supersession |
SPP_PDEM_SUPERSESSION_RLG |
--- |
Promotion |
SPP: Data Realignment for Promotion |
SPP_PDEM_PROMOTION_RLG |
--- |
Change to periods in the calendar master data |
SPP: Calendar Change Realignment |
SPP_PDEM_CLD_RLG |
SPP_CLD_CHG |
Change to final demand |
SPP: Adjustment of Demand History |
SPP_PDEM_OVR_RLG |