Performance-based Completion Confirmations from Production
Purpose
This step demonstrates how completion confirmations for a production order can influence maintenance measures performed on production resources and tools.
This example has been created for a bottling/canning plant. Here, tins are filled with paint. The bottling/canning plant contains a filter press which is recorded as PRT equipment in the task list for material Y-351.
The maintenance plan for the PRT equipment contains three performance related maintenance cycles. This means that every time the PRT equipment above is used, different operations are used for the scheduled maintenance plan. In cases of high use this may lead to a change of filter.
Process Flow
You can find the data for this process under
.