Displaying the Measurement Document 

Use

The starting situation for scheduling of production resources and tools (PRT equipment) is displayed.

Procedure

  1. Use the following procedure to call the transaction:
  2. Menu Path

    From the Plant Maintenance node, choose Management of Technical Objects ® Equipment ® Measurement Documents ® Display

    Transaction Code

    IK13

  3. Delete the entry in the field Measurement document and choose F4 help.
  4. Enter the following data:
  5. Field

    Data

    Description

    Measuring Point

    10171

    The measuring point is stored in the maintenance plan.

    Date to

    Today’s date

     
  6. Choose .
  7. You see a list of existing measurement documents.

  8. Select the most recent measurement document (with today’s date) and choose Goto ® Measurement document.
  9. This screen allows you to check the data in the completion confirmation for the order.

  10. Choose until the overview tree appears.