Changing the Order 

  1. Use the following procedure to call the transaction:
  2. Menu Path

    From the Plant Maintenance node, choose Maintenance Processing ® Order ® Change.

    Transaction Code

    IW32

    The system defaults the last order you processed.

  3. Choose .
  4. Choose the Operations tab page.
  5. Enter the following data for operation (Op.) 0030:
  6. Field

    Data

    Short text operation

    Replace intake sealing ring

  7. Select operation 0030.
  8. Choose Internal.
  9. Enter the following data:
  10. Field

    Data

    Ctrl key (Control key)

    PM01

    Work

    0,3

    Normal duration

    0,3

  11. To display scheduling for the order, choose the tab page Dates.
  12. Choose to return to the screen Change Maintenance Order: Operation Overview.
  1. Do not leave this screen.