Dates and Work
Here you can edit the dates for the following project elements:
Project definition
Task
Checklist item
Phase
Version (simulation or snapshot)
Project template
You can edit the work for the following project elements:
Checklist item
Task
You have specified how milestone tasks are to be scheduled by making the appropriate entry for area 0007
General Default Values
, setting 0041
Activate Fixed Values for Milestones
in Customizing for SAP Portfolio and Project Management
under . For more information, see the documentation of the Customizing activity.
You have created one of the project elements listed above (see Creating Project Elements) and are in the maintenance view of this project element on the Dates and Work
tab. You cannot make any changes if you opened a snapshot. You have created roles (see Creating a Role). In the Language
field (upper right-hand corner), you selected the language you want to use for creating language-dependent texts (see also Multilingual Capabilities).
You can define the earliest and latest dates as forecasted dates for a project element. To do this, choose Copy to Forecasted
. If you want to do this for a project element and all its lower-level elements, choose Copy to Forecasted
in the toolbar and define if the earliest or the latest dates shall be set.
Unlike normal tasks, milestone tasks do not represent a processing step but points that are significant for the progress of the project. For this reason, you can decide in Customizing whether or not milestones should have the same dates and be scheduled in the same way as normal tasks (see Prerequisites). The following options exist:
Milestones can be treated as a single point in time. In this case, the milestone task has a fixed duration of 0. It only has one date, the finish date, which is displayed in the graphical view of projects using the special milestone symbol.
Milestones can have a fixed duration greater than 0. In this case, the milestone task has a start date and a finish date, but it can only have a start constraint. In the graphical view, only its start date is displayed.
Milestones can have the same dates and be scheduled like normal tasks. In the graphical view, only their start date is displayed.
For more information, see Creating Basic Data for a Task.
You carry out the following activities for the project elements:
Project Element | Activities |
|---|---|
Project definition Version (simulation or snapshot) | Dates Area You enter dates in the If you do not enter any dates, the system uses the current date as the start date. The field for the finish date remains empty. The system calculates the finish date from the remaining project data during scheduling. Provided that the project has the status You select the The calendar influences scheduling. You use it to determine, for example, whether all weekdays or only working days are taken into consideration. You can choose Copy to Forecasted to set the earliest and latest dates as forecasted dates for the project definition, if required. |
Phase | Dates Area You select constraints. You enter a start date and a finish date, as required. The fields are only ready for input if you selected the You enter a The field is taken into account only if you have not entered a date or have only entered one date in the You select the You can choose You can choose |
Task | Dates Area You select the calendar that you want to use for this task. You select a constraint type for the start or finish date and specify the corresponding constraint dates as required. You can also choose You specify the forecasted dates. You can also choose You enter a duration, as required. The start or finish dates of the task are adjusted automatically. Note, however, that you cannot change the duration if the task has both a
If your task is a milestone, you may not be able to maintain all this data. Depending on your Customizing settings, the duration or one of the constraints may not be available for input. For more information, see above in the Features section under End of the note. Confirmation Area The fields in this area only become relevant once you confirm a task (see Confirming Tasks). They are ready for input once the task has the status
The tab End of the note. |
Checklist Item | Dates Area You select a constraint for the finish date. You enter a finish date, as required. This field is only ready for input if you have chosen the You can choose You can choose Confirmation Area You leave the You enter a value for the severity (see Failure Modes and Effects Analysis (FMEA)). You enter a value for the detection (see Failure Modes and Effects Analysis (FMEA)). You enter a value for the occurrence (see Failure Modes and Effects Analysis (FMEA)).
The three FMEA fields are ready for input once the checklist item has the status End of the note. |
Note
You can also edit the dates in the graphical view (see Graphical View) or in the table view (see Table View).