Conversion Log
Log that documents the process Changing an Equipment History
The conversion log is subdivided into several folders:
· General documents the entire process flow:
¡ Start and finish of the individual phases
¡ Scheduling and execution of the background jobs for phase 2
¡ Result of the central check (whether SAP ECC Extension PLM is activated)
¡ Deletion of the interim status
· History documents:
¡ Replacement of the actual history with the target history
¡ Adjustment of change documents
· Measurement Documents documents:
¡ Result of the check (whether relationships must be created for the measurement reading transfer)
¡ Individual measurement documents
· Structure Gap documents:
¡ Result of the check (whether the prerequisites for structure gaps have been met)
¡ Deletion and creation of structure gaps
· Goods Movements documents:
¡ Result of the check (whether the prerequisites for goods movements have been met)
¡ Creation of material documents
· CRM Coupling documents:
¡ Result of the check (whether CRM coupling is activated)
· Asset Coupling documents:
¡ Result of the check (whether the synchronization of fixed assets and equipment is activated)
· Notifications documents:
¡ Result of the check (whether the prerequisites for notification adjustment have been met)
¡ Creation and deletion of notifications
¡ References to notifications