  Solving Scheduling Problems

Use

After you have identified the scheduling problems in the detailed scheduling planning board , you try to solve these problems. In the planning board, there are several functions, in addition to manual rescheduling with Drag&Drop and detailed scheduling heuristics , which you can use to automatically execute certain scheduling steps, or which support you in other ways during scheduling. These functions are as follows:

Function

Use

Process Orders

When you want to create or delete orders, change the order quantity, or switch the source of supply

Scheduling or Rescheduling Operations and Orders using Drag&Drop

When you want to manually schedule or reschedule operations and orders

Deallocating Operations and Orders

When you want to (temporarily) remove individual operations and orders from the resource schedule

Rescheduling Operations and Orders

When you want to schedule or reschedule operations and orders and be supported by the system

Scheduling Operations in Non-Working Times

When you want to complete an operation or order with short notice outside of the regular working time

Fixing Operations, Orders, and Time Intervals

If you do not want it to be possible to change operations and orders as far as date/time and resource assignment are concerned, or to change the schedule of a resource in a specific interval

Interrupt Started or Partly Confirmed Operations

When you want to reschedule an operation that has started or has been partly confirmed

Backlog Rescheduling Heuristic

When you want to reschedule operations and orders that lie in the past

Sequencing Heuristic

When you want to reschedule operations and orders in a certain sequence that you have defined using sort criteria

Manual Sequencing Heuristic

When you want to reschedule operations and orders in a certain sequence that you have defined manually

Optimizing Scheduling

When you want to optimize scheduling with regard to certain criteria, such as setup times

Loading Alternative Resources

When you want to reschedule operations on alternative resources in the planning board

Changing Detailed Scheduling Strategies

When you cannot solve the scheduling problem with the current detailed scheduling strategies

Displaying and Changing Scheduling Data of Objects

When you want to change the scheduling data for the resources, for example

Displaying Logs

The following logs are available, if you want to find out which problems occurred (if at all) during scheduling, planning or optimization:

  • Scheduling log

  • Planning log

  • Optimization log

For more information, see Detailed Scheduling Activities .