Processing Orders on the Detailed Scheduling Planning Board The following functions are available for order processing in the DS planning board through the menu and the context menu for objects:
Create orders or create planned orders using reference
Delete orders
Change order quantity
Switch the source of supply for the order
Note
From the DS planning board, you can also go to order processing or the product view from the menu, or the context menu of a graphical object or table row.
To create an order within the DS planning board, you choose
Create Order
in the menu under
or in the context menu of a graphical object or table row
.
If you have already selected objects, the system tries to determine a product and a location from these, and offers them as a proposal in the dialog box that appears. If neither a product nor a location can be derived, the system either does not propose any values, or it proposes the last values entered in this dialog box. You can adopt or change these default values. In addition, you enter the desired date/time, the receipt quantity and the PP strategy, which the system should use for scheduling the order.
Caution
You cannot create an order with a negative receipt quantity as you cannot create planned independent requirements on the DS planning board. You can create planned independent requirements in the product view.
See also: Creating Planned Orders By Reference
To delete an order, select the table rows in the operation or order charts or graphical objects and then choose
Delete Order
in the
menu path or in the context menu
.
Note
To select several objects, press the shift key while choosing using the mouse and when invoking the context menu.
A list then appears containing all the orders determined for the selected objects, from which you can select the orders that you want to delete. In the list, the sort, search, and selection functions of the
SAP List Viewer
(ALV) are available.
Example
If you want to delete all orders for a certain product, sort the list according to the
Product
column, and then select the desired rows.
To change the order quantity, select a graphical object and choose
Change Order Quantity
in the
menu path or in the context menu
.
The system displays the current order data in a dialog box. Specify the desired order quantity and the PP strategy that the system is to use to reschedule the order.
The system reschedules the order in accordance with this data.
To switch the source of supply for an order, select a graphical object and choose
Switch Source of Supply
under
or in the context menu
.
In the
Source Determination
dialog box that then appears, choose one of the valid procurement alternatives.
The system reschedules the order with the new source of supply.
It is possible to set the conversion indicator for planned orders and purchase requisitions. You can set the indicator via either or the context menu. You can unset the indicator via or via the context menu.
The orders are converted after the planning situation has been saved.
It is also possible to got to the receipts view for selected objects and set the conversion indicator there. Choose