Entering content frameFunction documentation Budget Consistency Locate the document in its SAP Library structure

Use

This function ensures that the budget stored during budget allocation, updates, and releases are always consistent.

In the standard system, you can only save a budget allocation that is completely free of errors. This applies to all budget versions. In the customizing of Funds Management Government you can deactivate the automatic budget consistency for an FM area and a fiscal year in the step Deactivate budget consistency for annual values and Deactivate budget consistency for overall values. Having done this, you can then save your input, even if it is inconsistent.

You should only deactivate the automatic consistency check if, for example, you want to enter an initial budget allocation for a new fiscal year, but the exact budget allocation for individual funds centers and commitment items is not yet fixed. To ensure that the budget is consistent later, you can total up the budget values up to the top node.

You can check the budget consistency of already save budget versions at any time using program BPDIST04.

Features

To ensure that budget allocation is free of errors, the system checks whether the following conditions are met for each FM account assignment:

Within the hierarchy or subhierarchies, the budget value in the superior levels must be at least as much as the total of the budget values in the subordinate levels (= distributed value on the superior level).

If you are using the Distribute budget function to distribute budget within the hierarchy or subhierarchies, the sender funds center and commitment item must be on a higher level than the receiver.

This graphic is explained in the accompanying text

The total of the annual values per funds center/commitment item combination must not exceed the overall value for that combination. This check is only carried out if you are using annual and overall values. The parameter „Overall value" must be active in the Budget Profile.

This graphic is explained in the accompanying text

This graphic is explained in the accompanying text

The transfer amount may not exceed the current budget in the sender. Releases already made cannot be transferred.

This graphic is explained in the accompanying text

However, if you have activated automated Release in Customizing, the maximum amount that can be transferred from the sender is the amount that has already been released.

If you are working with parked budget, the consistency check is also carried out using the total of the current and parked budget. For more information, read Budget Parking.

Negative budget is only permitted if you have entered negative budget values in the FM account assignments provided for them or if negative residual budget is carried forward from the old year to the new year in the Budget Carryforward during year-end closing operations resulting in negative values in the new year. Otherwise, all budget values must be positive.

For more information on entering negative budget values, see Negative Budget.

If availability control is active, the system compares the budget values with the assigned values (actual plus commitment) and triggers the appropriate action (warning, warning with mail to budget manager, error message) if the tolerance limits defined for the budget are exceeded.

Activities

To actively check the budget consistency after budget allocation, choose the corresponding activity (Budget/Supplement/Return) ® Check in the respective transaction.

In the event of an error, the following happens:

To check the budget consistency of a budget version that you have already saved, execute the Budget consistency check program (BPDIST04). To do this, choose Accounting ® Public Sector Management ® Funds Management ® Information System ® Analyses ® Budget ® Budget Consistency Check.

 

 