Entering content frameProcess documentation Negative Budget Locate the document in its SAP Library structure

Purpose

If it is likely that you will have to reduce the budget originally planned in the overall budget, you can create special FM account assignments and enter negative budget values in them. The advantage of this is that the old budget remains valid, even though all of the data is not known when you are planning the budget.

This situation may occur if expenditures in the budget must be reduced, but it is not possible to determine which expenditure items can be decreased. It may be necessary to reduce the expenditure budget because a fall in revenue is expected or because tax revenues must be managed for other political organizations and passed onto the tax creditors.

Caution

The position management cannot process negative budget. This is important for customers who use components Funds Management Government and Position Management together.

Process Flow

  1. If you want to enter negative budget values for certain FM account assignments, you must flag these FM account assignments, as they are subject to special budget consistency and availability control requirements. For more information, see Master Data for Negative Budget.
  2. You enter the negative budget values. For more information, see: Entering Negative Budget.
  3. During the course of the year the budget is used up through assigned funds. The budget manager can transfer post budget that is not needed for expenditures FM account assignments to FM account assignments with negative budget values. In this way he can clear these FM account assignments; that means that the negative values are brought back to zero. For more information on this, see Example: Global Expenditure Shortfalls.
  4. The evaluation of negative budget values is possible with the help of various programs:

Result

The budget originally planned in the overall budget is reduced with the help of negative budget values. On the one hand this prevents the inflation of budget values. On the other hand negative budget values can be used to map Global Expenditure Shortfalls and through this the budget execution has a more flexible structure.