Entering content frameFunction documentation Valuation Locate the document in its SAP Library structure

Use

You can activate the valuation for WCM-relevant orders so that the maintenance workers can decided themselves, whether safety measures must be implemented.

For the valuation you must define explicitly for each application whether or not it is necessary.

Prerequisites

In Customizing for Work Clearance Management you have defined the following:

Features

If the valuation is activated and the applications are defined, then every WCM-relevant order must be valuated, that is, you must specify during the processing of an order whether or not it is necessary for each application.

As soon as at least one application is valuated, the order is solely WCM-relevant.

During the valuation the system checks whether you are authorized to valuate the application. It also document who performs the valuation at what time.

You can change a valuation until "Released for execution" (Status EXEC – Released for execution) is issued.

As soon as you have valuated all the applications, the system sets the status VAL (Valuated) in the order.

The valuation is the basis of the "Released for execution", that is, the applications valuated with Yes are mandatory.

Activities

  1. Activate Work Clearance Management for the order.

The order is now WCM-relevant and the pushbutton Valuation is displayed.

  1. Choose Valuation.

This takes you to the dialog box with the applications to be valuated.

  1. When you have valuated all the applications, the system sets the status VAL (Valuated) in the order:

The pushbutton "Release for execution" appears in the order and you can set the status EXEC (Released for execution).

A work clearance application must be assigned to the order, and for this the approval status must be green. Only then does the pushbutton "Release for execution" appear in the order and you can set the status EXEC (Released for execution).

A work approval with the applications that were valuated with Yes must be assigned to the order. The work approval must have the approval status green. Only then does the pushbutton "Release for execution" appear in the order and you can set the status EXEC (Released for execution).

Leaving content frame