Problem

Solution

The system does not allow you to create or maintain planning delivery schedules

Check that you have entered an instruction in the scheduling agreement

The system does not allow you to maintain any sort of delivery schedule in the scheduling agreement

Check that you have not deleted in Customizing the planning delivery schedule instruction for the scheduling agreement

No schedule lines are generated in the planning delivery schedule

Check that you have:

  • Entered split shares
  • Set the automatic indicator

    Note: Even if you have marked this indicator, the system performs the automatic function if you create or change a planning delivery schedule manually.

Unexpected schedule lines quantities in the planning delivery schedule

Check your settings for the:

Unexpected schedule line dates

Check your settings for the:

Schedule lines in the planning delivery schedule do not correspond to your required planning period

Check your settings for the:

Unexpected split end date

Check your settings for the:

Schedule lines from the forecast delivery schedule are copied but not split

Check that you have assigned a:

Unexpected requirements or delivery relevance for schedule lines in the scheduling agreement

Check your settings for the delivery relevance. Also review the instruction that you have entered in the scheduling agreement.

Schedule lines in the previous planning delivery schedule are not copied to the new schedule

Check that you have set the adopt schedule lines indicator

 

 