Planning for Components to be Provided in Subcontracting 

Use

Using the MRP area, you can plan the provision of components for individual subcontractors separately from the usual requirements (see also Subcontracting).

Prerequisites

Features

During the planning run, the system explodes the BOM of the assembly to be manufactured and determines the requirements for components that are to be provided to the subcontractor X. The dependent requirements of the components to be provided are only assigned to the MRP area of the subcontractor when the system can determine the subcontractor as the source of supply for the assembly. The source of supply is determined using the source list.

Depending on the requirements situation and the settings entered, the system creates either