Stock Transfer of Components to be Provided 

Use

You can procure the components that you provide to a subcontractor for the production of an assembly, by transferring stock from a plant to the MRP area of the subcontractor.

Prerequisites

Features

During the planning run, the system determines the subcontractor X as the vendor for the assembly using the source list and creates a purchase requisition for the assembly.

The BOM of the assembly is then exploded. The dependent requirements of the components to be provided are assigned to the MRP area of the subcontractor X.

Due to the special procurement key in the MRP area segment of the components to be provided, the system determines that the components are to be procured by means of stock transfer from the plant to the MRP area. A stock transfer reservation is created in this situation. This type of reservation is the movement type 541.

Using the evaluation SC Stock Monitoring for Vendor (transaction ME2O), you can display the reservations of the components to be provided and post the goods movement.