Subcontracting/Third-Party Order Processing 

Use

If you plan for the components to be provided for a subcontractor with an MRP area of the subcontractor type and the components to be provided are procured externally, you can process the procurement of these components using subcontracting/third-party orders.

This type of processing has the advantage that the required components to be provided are delivered directly from the vendor, from whom you order this material, to the subcontractor.

Prerequisites

Features

During the planning run, the system determines the subcontractor X as the vendor for the assembly using the source list and creates a purchase requisition for the assembly.

The BOM of the assembly is exploded. The dependent requirements of the components to be provided are assigned to the MRP area of the subcontractor X.

The system creates one or several purchase requisitions (depending on lot size) for the dependent requirements, which you can convert to purchase orders. These purchase orders are subcontracting/third-party orders.

When you display a subcontracting/third-party order, you will see the subcontractor’s address in the space for the delivery address. The SC stock indicator X for stock with subcontractor is set. The item type and account assignment type fields do not contain any values.

Activities

The components to be provided are delivered directly to the subcontractor. The goods receipt is posted to the stock with subcontractor.

When the subcontractor has delivered the finished assembly, the goods receipt is posted to the subcontract order. The stock with subcontractor and the reservations are then reduced.