Call History 

Overview

When you generate a call in a maintenance plan, the system records it either one of two displays:

This enables you to trace both scheduled and manual call dates at any time and is particularly important for critical technical systems, for example, in the case of unforeseen shutdowns or damage which could have had an effect on dates in the past or which could effect future call dates.

Procedure

You can display scheduled and manual calls from the maintenance schedule screen in your maintenance plan. To display calls, perform the following three steps:

  1. In the Maintenance Planning menu, call up the change, display or schedule transaction, using one of the following menu paths:
  2. Prev.MaintPlans ® Change

    Prev.MaintPlans ® Display

    Time scheduling ® Schedule

  3. Enter your maintenance plan and choose Continue.
  4. You are now on the maintenance schedule screen.

  5. To display the call history, choose one of the following options:

Goto ® Display calls ® Scheduled calls

Goto ® Display calls ® Manual calls

Display Call Components

The displays are made up of the following components:

Working with the Call History

The following functions are available for the call history: