Call Date

The call date is the date on which a maintenance order is created in the system. This is determined by the call horizon of the maintenance plan.

Maintenance package: Monthly, Call horizon: 50%, Start: August 31, 1995

Planned date:

September 30, 1995

Call date:

September 15, 1995