 Changing Slot Activity Relationships

Use

You can change the sequence in which slot activities are carried out in a slot task list by changing the activity relationships.

Prerequisites

You have created a slot task list and slot activities.

Procedure

  1. On the SAP Easy Access screen, choose Start of the navigation path Advanced Planning and Optimization Next navigation step Master Data Next navigation step Master Data for Maintenance and Service Planning Next navigation step Maintenance Task List End of the navigation path .

  2. Open the required task list and double-click on the task list node.

  3. On the Activities tab, choose Network Graphic , select the line connecting the first two activities for which you want to change the relationship and choose Delete Object Relationship .

    The line connecting the two activities is deleted.

  4. Repeat the previous step for the other activities for which you want to change the relationship.

  5. Choose Create Object Relationship , select the right-hand side of the activity you wish to place first in the relationship, and drag the cursor to the left-hand side of the activity you wish to place second.

  6. Repeat the previous step for the other activities for which you want to change the relationship.

  7. Choose Rearrange Horizontally to place the activities in the correct sequence.

  8. Choose Close Network Graphic to return to the Activities tab.

See also:

Opening a Maintenance Task List

Defining a Task List

Defining an Activity in a Task List

Resources and Locations in MSP

Creating Modes and Assigning Resources in a Task List Activity