Technical Name: 0PP_C03_Q007
Use
This query displays the capacity load utilization of a work center. However, you should note that a capacity requirement generated by an operation is not distributed across several days. Therefore, the query should be called up for longer periods of time, since inaccuracies can occur at the margins of the selection period.
The available capacity is available per work center. This should be noted when drilling down on orders and operations. The SCOR key figure
Machine Wait Time shows you the proportion of a work center’s unused capacity in relation to the total capacity.Contrary to query 0PP_C04_Q001, the actual release date is used as the date of the capacity requirement of an operation instead of the date of the first confirmation. The query 0PP_C04_Q001 is normally the more suitable for evaluation purposes, especially if the actual release date differs greatly from the confirmation date.

If you have an R/3 Release from 4.0B onwards, SAP recommends that you use query
Freely-Defined Characteristics
|
InfoObject |
Description |
|
0WORKCENTER__0WRKCT_RESP |
Person responsible |
|
0WORKCENTER |
Work center, variable &0S_WORKC2& |
|
0MATERIAL |
Material, variable &0S_MAT& |
|
0PRODORDER |
Order |
|
0OPERATION |
Operation |
|
0S_OPERAT |
Suboperation |
|
0CALMONTH |
CalYear/Month, variable &0I_CALMO& |
|
0CALDAY |
Calendar day |
Rows
|
InfoObject |
Description of InfoObject (or Restriction or Calculation Formula) |
|
0PLANT |
Plant, variable &0S_PLANT& |
Columns
|
InfoObject |
Description of InfoObject (or Restriction or Calculation Formula) |
| 0C_T_CAPACITY |
Target capacity requirement |
| 0C_T_CAPAUTIL_% |
Target capacity load utilization |
|
0STANDCAP |
Available capacity |
| 0C_T_WAIT_TIME_PP03 |
Relative target wait time |