QueryCapacity Load Utilization  Locate the document in its SAP Library structure

Technical Name: 0PP_C03_Q007

Use

This query displays the capacity load utilization of a work center. However, you should note that a capacity requirement generated by an operation is not distributed across several days. Therefore, the query should be called up for longer periods of time, since inaccuracies can occur at the margins of the selection period.

The available capacity is available per work center. This should be noted when drilling down on orders and operations. The SCOR key figure Machine Wait Time shows you the proportion of a work center’s unused capacity in relation to the total capacity.

Contrary to query 0PP_C04_Q001, the actual release date is used as the date of the capacity requirement of an operation instead of the date of the first confirmation. The query 0PP_C04_Q001 is normally the more suitable for evaluation purposes, especially if the actual release date differs greatly from the confirmation date.

Note

If you have an R/3 Release from 4.0B onwards, SAP recommends that you use query 0PP_C13_Q001 for capacity evaluations.

Freely-Defined Characteristics

InfoObject

Description

0WORKCENTER__0WRKCT_RESP

Person responsible

0WORKCENTER

Work center, variable &0S_WORKC2&

0MATERIAL

Material, variable &0S_MAT&

0PRODORDER

Order

0OPERATION

Operation

0S_OPERAT

Suboperation

0CALMONTH

CalYear/Month, variable &0I_CALMO&

0CALDAY

Calendar day

Rows

InfoObject

Description of InfoObject (or Restriction or Calculation Formula)

0PLANT

Plant, variable &0S_PLANT&

Columns

InfoObject

Description of InfoObject (or Restriction or Calculation Formula)

0C_T_CAPACITY

Target capacity requirement

0C_T_CAPAUTIL_%

Target capacity load utilization

0STANDCAP

Available capacity

0C_T_WAIT_TIME_PP03

Relative target wait time

 

 

End of Content Area