Target Capacity Requirements  Locate the document in its SAP Library structure

Technical name: 0C_T_CAPACITY

Use

Plan/actual comparison operation/work center view: This InfoObject calculates the sum of the target capacity requirements setup, process and teardown.

Distribution across several periods, as is the norm in capacity planning, does not take place. Evaluation only makes sense, therefore, over a large selection period or for operations that are processed within a day.

Note

From R/3 Release 4.0B, the key figure 0C_T_CAPACITY_PP13 is to be used for capacity evaluations.

Technical Data

Available from Release

R/3 Release 3.0F

Calculation

"target capacity setup" + "target capacity processing" + "target capacity teardown"

 

 

 