Technical name: 0C_T_CAPACITY_PP13
Use
Capacity load utilization:
This InfoObject calculates the sum of the target capacity requirements setup, process and teardown.An attempt is made to divide the capacity requirements equally between the working days (see Capacity Load Utilization).
Technical Data
|
Available from Release |
R/3 Release 4.0B |
|
Calculation |
"target capacity requirements operation segment teardown" + "target capacity requirements operation segment process" + "target capacity requirements operation segment teardown" |