 Sample Scenario: Strategy 52

Process Flow

This example is based on a production plan in which 100 pieces are planned for <reqdat1>, <reqdat2>, and <reqdat3>.

The BOM structure for this example has a parent material SZ-52 and a component ROH52A . The BOM has an item quantity of 1.

Stage 1: Demand Management

  1. Planned independent requirements are created for the production plan. For information on how to create planned independent requirements, see Creating Planned Independent Requirements with Reference or Creating Planned Independent Requirements Without a Reference .

    The system finds requirements type VSE because the strategy group has been set to 52 .

    See the Table of Planning Strategy Assignments .

  2. The requirements are passed on to MRP. The stock/requirements list ( Start of the navigation path Logistics Next navigation step Production Next navigation step MRP Next navigation step Evaluations Next navigation step Stock/reqmts list) End of the navigation path for the finished product displays the following information:

    Date

    MRP element

    MRP element data

    Received/ required quantity

    Available quantity

    <today>

    Stock

    0

    <today>

    ⇒ Planning w/o assembly

    <reqdat1>

    IndReq

    VSE

    100 -

    100 -

    <reqdat2>

    IndReq

    VSE

    100 -

    200 -

    <reqdat3>

    IndReq

    VSE

    100 -

    300 -

Stage 2: Procurement Before Sales

  1. Procurement requisitions are created in the MRP run ( Start of the navigation path Logistics Next navigation step Production Next navigation step MRP Next navigation step Total planning End of the navigation path ). The stock/requirements list for the finished product displays the following information:

    Date

    MRP element

    MRP element data

    Received/ required quantity

    Available quantity

    <today>

    Stock

    0

    <today>

    ⇒ Planning w/o assembly

    <reqdat1>

    PlOrd.

    1234/IndR

    100

    100

    <reqdat1>

    IndReq

    VSE

    100 -

    0

    <reqdat2>

    PlOrd.

    1235/IndR

    100

    100

    <reqdat2>

    IndReq

    VSE

    100 -

    0

    <reqdat3>

    PlOrd.

    1236/IndR

    100

    100

    <reqdat3>

    IndReq

    VSE

    100 -

    0

    These procurement requisitions are the starting point for production or external procurement. Various possibilities exist for handling the procurement process in the SAP system. The following factors, however, are important for this strategy:

    Stock at finished product level is not taken into account for production.

    The planned orders are not yet “real” because production of the finished product must be executed after receipt of the sales orders. The planned orders have order type (VP).It is impossible to convert these (VP) planned orders into production orders, or to use them in a repetitive manufacturing environment.The Conversion field in the display of the planned order is not set, which indicates that it is not possible to produce this planned order.

  2. The MRP run also creates procurement requisitions for the components. In this example, the stock/requirements list for the component ROH52A displays the following information:

Date

MRP element

MRP element data

Received/ required quantity

Available quantity

<today>

Stock

0

<reqdat1>

PlOrd.

1237/Stck

100

100

<reqdat1>

DepReq

SZ-52

100 -

0

<reqdat2>

PlOrd.

1238/Stck

100

100

<reqdat2>

DepReq

SZ-52

100 -

0

<reqdat3>

PlOrd.

1239/Stck

100

100

<reqdat3>

DepReq

SZ-52

100 -

0

  1. The main objective of this strategy has now been reached: procurement for the components has been triggered, even without sales orders, due to Demand Management alone. Procurement of the components can occur in a variety of ways. Here we are assuming that a goods receipt (for a purchase order, for example) takes place. The stock/requirements list for all components of the material displays the following information:

    Date

    MRP element

    MRP element data

    Received/ required quantity

    Available quantity

    <today>

    Stock

    300

    <reqdat1>

    DepReq

    SZ-52

    100 -

    200

    <reqdat2>

    DepReq

    SZ-52

    100 -

    100

    <reqdat3>

    DepReq

    SZ-52

    100 -

    0

Stage 3: Sales Order and Allocation

  1. A sales order for the parent material is created.

    The system will find the requirement type KSVS because the strategy group has been set to 52 . See the Table of Planning Strategy Assignments .

    It is possible to confirm a quantity that has been previously planned (100 pieces for each schedule line, in this example) . The header text that says Assignment of Planned Independent Requirements indicates that this is not a check according to ATP logic but rather an availability check based on planned independent requirements.

    The system finds the schedule line category CP and the item category TAN because the item category group was set to NORM.

    Suppose that for this example an order with a quantity of 90 pieces is entered with a required delivery date of today. This order can be confirmed after the first planned independent requirement date <reqdat1> if the consumption parameters have been defined accordingly and this date can be found. For more information, see Consumption Strategies and Logic .

  2. After entry of the sales order, the stock requirements list for the parent material displays the following information:

    Date

    MRP element

    MRP element data

    Received/ required quantity

    Available quantity

    <today>

    Stock

    0

    <today>

    Order

    000333/0010/001

    90 -

    <today>

    ⇒ Planning w/o assembly

    90 -

    <reqdat1>

    PlOrd.

    1234/IndR

    100

    100

    <reqdat1>

    IndReq

    VSE

    10 -

    90

    <reqdat2>

    PlOrd.

    1235/IndR

    100

    190

    <reqdat2>

    IndReq

    VSE

    100 -

    90

    <reqdat3>

    PlOrd.

    1236/IndR

    100

    190

    <reqdat3>

    IndReq

    VSE

    100 -

    90

Stage 4: Procurement After Sales

  1. After a second planning run, the stock/requirements list of the parent material displays the following information:

    Date

    MRP element

    MRP element data

    Received/ required quantity

    Available quantity

    <today>

    Stock

    0

    <today>

    Order

    000333/0010/001

    90 -

    90 -

    <t+rlt>

    PlOrd.

    1237/Stck

    90

    0

    <today>

    ⇒ Planning w/o assembly

    0

    <reqdat1>

    PlOrd.

    1234/IndR

    10

    10

    <reqdat1>

    IndReq

    VSE

    10 -

    0

    <reqdat2>

    PlOrd.

    1235/IndR

    100

    100

    <reqdat2>

    IndReq

    VSE

    100 -

    0

    <reqdat3>

    PlOrd.

    1236/IndR

    100

    100

    <reqdat3>

    IndReq

    VSE

    100 -

    0

    The planned order (“Stck”) for the parent material can now be converted to either a production order, a process order, or allow backflushing in the repetitive manufacturing process. This triggers the production after sales order stage. Production of this material can be performed quickly because all the necessary components are already available.

  2. After creation and release of the production order (for the parent product) the stock/requirements situation remains the same. This means that the planned order is replaced by a production order.

    Note Note

    Working with production orders is only one option for production. This process is also possible in the area of repetitive manufacturing.

    At component level (ROH52x), the dependent requirements (“DepReq” in the planned order) are replaced by an order reservation (“OrdRes” in a production order).

    End of the note.
  3. Perform a Goods Receipt for the parent material, after production.Note the increase in available stock in the stock requirements list of this material.

    Stage 5: Goods Issue for Delivery and Reduction of Planned Independent Requirements

After goods issue for the delivery (choose Start of the navigation path Logistics Next navigation step Sales and distribution Next navigation step Shipping Next navigation step Delivery Next navigation step Create End of the navigation path ) for the parent material, the stock/requirements list of the parent material is reset back to empty again. In other words, it only shows the planned independent requirements and the corresponding planned orders.The planned independent requirements are, of course, reduced.