Creating PIRs Without References To create a planned independent requirement without a reference, choose .
Note
In the
User Parameters
you can enter values, such as default values for the requirements that are to be created.
See Maintaining Requirements Parameters .
The system displays the initial screen for maintaining planned independent requirements.
Enter the material number, the name of the product group or the requirements plan.
Enter the plant (see Material Requirements Planning ).
Enter the version and choose
(
Continue
).
The system creates the planned independent requirements with this version number.
The system displays the screen where you can maintain planned independent requirements.
Check the parameters and change them if necessary.
Check the period indicator, and if necessary, change it.
Enter the requirements date and the planned quantity of the planned independent requirement.
For more information about the procedure, see the following table:
Function |
Procedure |
|---|---|
Split the total planned independent requirement quantity across periods (on the planning table or schedule line tab page) |
|
Use the interactive forecast to determine the planning quantities |
See Determining Planning Quantities Using the Material Forecast |
Assign production versions to schedule lines |
Choose . |
Assign BOM explosion numbers |
Choose . |
Define that the planned independent requirement is to be consumed and not planned in the net requirements calculation |
Select the field
|
Work with a configurable material for which usage probabilities are maintained |