You can use this process to configure your production routings to allow non-serialized SFCs to be in work at more than one operation at the same time. This allows an SFC to flow down a routing in the natural manner that physical product flows down your production line. Operators can complete partial quantity of a non-serialized SFC at any step on the relaxed routing.

Note Note

A partial quantity will be completed out of a simultaneous group only if that quantity has been completed at every other step within the group.

End of the note.

If you use the Auto-Split and Auto-Merge functionality, operators can also disposition a partial quantity of an SFC.

Process

  1. In Material Maintenance, set the Lot Size field for your material to a quantity greater than one. Set the Qty Restriction field to Any Number or Whole Number.

  2. In POD Maintenance, retrieve the POD you want to use and on the POD Selection tab page, select the Show Quantity checkbox. The Quantity field displays in the POD, allowing operators to enter a quantity less than the full SFC quantity in order to start, process, and complete the partial quantity of the SFC at that operation.

    Note Note

    To limit the number of SFCs created for an order, set the material’s lot size to equal or exceed the build quantity of the order. If build quantity is unpredictable, set the lot size to a large number. For example, 999999999 or greater.

    End of the note.
  3. In Routing Maintenance, you select the Relaxed Routing Flow checkbox for all production routings where you want to use relaxed flow.

  4. If desired, on the Build tab page in Material Maintenance, you select the Use Shop Order ID on First Release checkbox. The system uses the shop order ID in place of the SFC number when you first release quantity for the material to your production line.

  5. If you want operators to disposition SFCs from your relaxed production routing, in Activity Maintenance you retrieve the NC_DATA_ENTRY activity and set the AUTO_SPLIT option to ALWAYS or ASK. Retrieve the PR510 (Complete) activity and set the AUTO_MERGE option to ALWAYS or ASK

    Note Note

    Operators can also manually split and merge partial quantities with SFC Split and SFC Merge.