Start of Content Area

Background documentation Settings in the R/3 Material Master  Locate the document in its SAP Library structure

As well as the normal configuration of material master, you must make certain settings for the process to run as expected. When setting up the material master you must ensure that issuing a sales order for the material results in requirements in sales order stock. These requirements must consume forecasts in general plant stock.

The relevant settings are on the MRP tab pages in the standard system.

Tab page

Field

Required effect

Suggested Value

MRP 1

MRP type

MRP planning should not be carried out for the material. However requirements msut be transferred. This means you should not set value ND (no planning) in the standad system

X0

MRP 3

Strategy group

The strategy group must lead to a requirements class that has value 2 (Consume planning w/o assembly) for the Allocation indicator and stipulate the transfer of requirements.

To confirm the sales order, you must also set the Availability indicator in the requirements class

See also Link to external website Planning Strategies in the SAP Library for R/3 Demand Management.

SAP recommends a strategy without final assembly.

DO NOT use strategy 10 - for Make-to-Stock production (see Requirements Strategy)

MRP 3

Availability check

Check individual requirements

2

You can enter details for consumption here on the MRP 3 tab or in the product master in SAP APO. It is not important in which system you do this, but that you make the settings in one of the two systems. For more details, see Settings in the APO Product Master

See also:

This graphic is explained in the accompanying textDefiine Requirements Class in the SAP R/3 Implementation Guide.

This graphic is explained in the accompanying textMaterial Master in the SAP Library for SAP R/3

Note 143314 for more detailled information on the Integration of APO and R/3 ith respect to production planning.