Resource Planning Table
You can use the resource planning table to implement an interactive detailed scheduling of resources and orders of Production Planning and Detailed Scheduling (PP/DS).
The resource planning table represents an alternative to the detailed scheduling board. In contrast to the detailed scheduling board, which is a graphical tool, the resource planning table provides you with the information on the capacity utilization of resources in tabular form.
You can use the resource planning table to plan interactively in order to solve problems such as sequencing, overload, or scheduling problems on resources. For this purpose, a clipboard function is available to assist you in manually rescheduling the sequence of operations, plus various planning functions and heuristics.
You can use the resource planning table above all for the following planning tasks:
Sequencing
Backlog rescheduling
Capacity leveling
You invoke the resource planning table from the SAP Easy Access
screen under .
See also: Defining Selection Conditions for the Resource Planning Table
The following applications are integrated in the resource planning table:
Alert Monitor
You can call up the Alert Monitor in the resource planning table at any time to display scheduling problems.
Plan monitor
You can invoke the plan monitor in the resource planning board to evaluate the planning quality according to user-defined criteria and key figures.
Optimization
To optimize the planning, you can call up the optimization function in the navigation area in the resource pool.
The resource planning table is divided into the following screen areas:
Navigation area on the left side
Work area with the resource data on the right-hand side
You can show and hide the individual screen areas as desired.
In the navigation area, the following buttons are available enabling you to invoke the various objects:
Resources
From the list of resources displayed, you can select one whose details are then displayed in the work area. The chosen resource is marked with the quick info Displayed and Active
.
Clipboard
You can copy operations into the clipboard and change their sequence manually. You can then schedule the changed list of operations on the resource. To process the operation list, you can enlarge the navigation area so that all necessary columns are available.
Heuristics
The heuristics from the heuristic profile with which you invoked the resource planning table are displayed. You can start a heuristic for the objects selected in the work area with the quick info Execute
,
directly before the heuristic. You can start heuristics for a resource, for the operations of a period, or for certain operations in the operation list.
Changed Objects
You get a list of all objects that have been changed during the last planning/scheduling step: resources, operations, products, or orders.
Note
You do not see any deleted objects in the list.
In the work area, the information on the active resource is displayed. The work area is subdivided into three parts:
Header data
This chart shows you the key data on the selected resource.
Periodic view
This chart shows you information such as the available capacity and utilization of the selected resource in the display period.
Operation list
You see the operations and other information (such as non-working time, blocks) for the period you selected in the periodic view. You can process the operations with the various planning functions.
In the resource planning table, not only can you move operations and activities by Drag&Drop
, you can also use the Pick&Drop
function to move operations and activities between the individual charts without using the mouse
(see Scheduling or Rescheduling Operations with Pick&Drop).
You cannot schedule bucket or mixed resources because you can only display the time-continuous portion in the resource planning table.
You can only schedule multiresources to a limited extent because, here too, you can only display the temporal dimension and you cannot see from the resource planning table how much capacity is still free at a certain point in time.
You cannot display pegging relationships.
The Resource Planning Table is not intended to handle or to be used for business functions such as:
Planning of multiresources
Planning of bucket resources
Displaying network information (pegging, relationships)
The function can be called only from those transactions that call the Receipts View
screen, which includes the transactions:
/SAPAPO/RRP4 (Receipts View
)
/SAPAPO/RRP7 (Mass Conversion/Transfer of Planned Receipts in Active Planning Version
)
/SAPAPO/SNP2PPDS (Conversion of SNP Orders into PP/DS Orders
)
/SAPAPO/CDPS0 (DPS Variable View
) and other related transactions
/SAPAPO/RPT (Product Planning Table
)