Scheduling 

Use

After you have planned an order with all its operations and components, you can use the scheduling function to determine the following data:

This date is entered based on the start date for the operation, in which the material is required.

For more information, see Scheduling Data.

You cannot schedule sub-operations independently, since scheduling is performed at operation level.

For more information, see Changing of Time Zones.

Integration

If you have maintained specific relationships for an order, you should note the following:

If you do not want this, you can execute the function Generate relationships automatically. As a result, a relationship of FS-relationship type is generated between all the operations, between which no relationship has been created manually.

For more information, see Use of Relationships.

Prerequisites

Before the system can schedule an order, you must maintain the scheduling data.

Activities

The system can be configured by your system administration using Customizing in such a way that it schedules the order each time you save it. However, you can schedule the order on a trial basis during planning to see whether the data calculated is suitable. Refer to Scheduling an Order.