Changing Scheduling Data 

  1. Call up the order in change mode.
  2. Edit the basic dates on the central header data screen for the order.
  3. Edit the scheduling type on the Additional data tab page.
  4. Edit the control key and the performing work center for an operation in the order on one of the following screens:
  1. Edit the execution duration for each operation on the detail screen for internal processing.

You have the following options:

  1. Edit the scheduling restrictions on the Dates tab page.

See also: