Changing Scheduling Data
Call up the
order in change mode
.
Edit the
basic dates
on the central header data screen for the order.
Edit the
scheduling type
on the
Additional data
tab page.
Edit the
control key
and the
performing work center
for an operation in the order on one of the following screens:
Operation overview of the order
Detail screen for general data
Detail screen for internal processing
Edit the
execution duration
for each operation on the detail screen for internal processing.
You have the following options:
The execution duration is automatically calculated by the system from other entries. You find the result in the
Duration
field on the detail screen.
You enter the execution duration manually.
Edit the
scheduling restrictions
on the
Dates
tab page.
See also:
Scheduling an Order
Assigning an Order to a Project