Completing the Initial Test

Use

You complete the initial test by making the usage decision for the inspection lot. This usage decision determines whether or not the stability study will be continued. When you make the usage decision, you can choose between the following usage decision codes:

  • Complete initial test: Stability study will be continued

If you choose and save this usage decision, the system automatically executes a follow-up action that sets the user status Initial Test Completed in the stability study.

  • Complete initial test: Stability study will not be continued

If you choose and save this usage decision, the system also executes a follow-up action automatically that sets the user status Initial Test Completed in the stability study. Furthermore, the system will branch to the stability study in the change mode as soon as you have saved the usage decision. In this way, you can manually trigger additional follow-up functions in the action box (for example, to cancel or complete the stability study, to print lists, and so on).

Note Note

The usage decision codes and corresponding follow-up functions described above are examples provided by SAP in the delivery system.

If necessary, you can define your own:

End of the note.
  • Selected sets with usage decision codes for the initial test

  • Follow-up actions for the usage decision

If you choose to do this, it is important that the status Initial Test Completed is set in the stability study, when the usage decision is made. If the system cannot set this status by means of the follow-up action for the usage decision (for example, because the stability study is currently being processed by another user and is locked), you can set this status manually in the stability study by executing a corresponding follow-up function in the action box.

Prerequisites

You have recorded inspection results for all characteristics, valuated and closed all characteristics, and saved the inspection results.

Procedure

  1. From the SAP Easy Access menu, choose Start of the navigation path Logistics Next navigation step Quality Management Next navigation step Stability Study Next navigation step Stability Test Next navigation step Usage Decision Next navigation step Record End of the navigation path .

The initial screen for recording the usage decision appears.

  1. Enter the inspection lot number and then choose Usage Decision .

The screen for recording the usage decision appears.

  1. Using the possible entries help, choose one of the following usage decision codes for the inspection lot:

  • Complete initial test: Stability study will be continued

  • Complete initial test: Stability study will not be continued

  1. Save the usage decision.

See also:

Making a Usage Decision

Result

The inspection lot for the initial test has been completed.

If you made the usage decision to: