Calling up the Dates OverviewYou have defined events in Customizing the Project System under .
You have assigned the relevant components and events to a group .
In the dates overview, the system only displays dates for components and events that have been assigned to a group.
If you are using a profile for monitoring dates and you have entered a
Group
in the profile, when you call up
Monitoring Dates
the system automatically generates a group that contains all the selected components. If you want to work with this group, you only have to assign it the relevant events.
Choose
Logistics
or
or
On the initial screen, enter the object(s) for whose components you want to monitor the dates. Such an object could be:
A
project
A
WBS element
or a range of WBS elements
A
network
or a range of networks
Choose
Dates
.
You can also call up the dates overview from the overview screens for groups, components, and events, if for instance you have previously checked or changed the groups.
An overview of the dates appears. This contains the dates for the components and events that are assigned to a group. Date variances are highlighted and have a traffic light displayed. You can also manually set statuses . You can filter or sort the overview according to various criteria.
If you have the necessary authorization, you can change the dates that the system does not derive from reference dates.
For more information, see Functions in the Dates Overview .