Manually Setting StatusesYou can manually set statuses per event and component. This allows you to subjectively assess whether, for instance, a delay that has been given a red light really is critical for the success of a project or whether it can be ignored.
You have defined statuses for events in Customizing for the
Project System
by choosing
You can only assign statuses to events for which at least one date has been set.
You can enter statuses on either the
Dates overview
or the detail screen.
Select the required component.
In the
Status
column for the required event enter the key of the relevant status. You can also use F4 help to display the descriptions of all the statuses that have been defined and to select one.
Choose
Enter
The status is set for the chosen event and component. If an icon has been assigned to the status in Customizing for the
Project System
, this icon appears in the
Dates overview
and the detail screen for the combination of component and event.