Planning and Publishing a Manufacturing Bill of Material (MBOM)

The next step in the process of handover is planning a manufacturing BOM.

Prerequisites

You've created a handover for an EBOM using Hand Over Engineering Bills of Material (EBOM) app from the launchpad for any of the following:

For more information, see Creating a Handover.

Context

When you create a handover, the app automatically navigates to the Handover From Engineering BOM Planner page. The app loads the source EBOM into the Source panel. By default, the root assembly from the Source panel is loaded into the Target panel. Choose Edit to perform any planning.

From the Handover From Engineering BOM Planner page, you can make your selections for planning and transferring the assemblies or components directly to the Target panel if no changes are to be made to the source EBOM structure.

For more information about the panels, see Panels.

Procedure

  1. To expand the multilevel hierarchy of the source EBOM, choose the context menu (More) → Load BOM or the Load BOM button from the header section of the Source panel. You can also select and load alternative BOMs of your choice for planning.
    For more information, see Loading BOM.
  2. Select the components or assemblies from the Source panel and choose the planning type that you want to use to move them to the Target panel. For more information, see Planning Types.
  3. Check the status of the planned components and assemblies.
    • In the Source panel, all the moved components or assemblies have the following statuses along with quantity statuses:
      • (Planned)

      • (Unplanned)

      • (Partially Planned)

      • (Consumed)

      • (Partially Consumed)

      For more information on the statuses, see Planning Statuses.
    • In the Target panel, all the planned components or assemblies may have the following statuses:

      Option

      Description

      (Not Yet Published to SAP S/4HANA System)

      If the components are not synchronized with the SAP S/4HANA System.

      (Quantity updated manually)

      Indicates that the component quantity in the Target panel was updated manually.

      (BOM is in use by another handover)

      Indicates that the BOM is currently being used in another handover.

      Change Reconciliation

      Indicate discrepancy in the attributes or values in the Target. You can use this workbench to resolve the discrepancy.

  4. Additional Steps
    Choose any of the following to perform in the Target panel:
  5. Select the assembly or component in the Target panel where you want to add a manufacturing-consumable component.
    1. In the Target panel, choose (Add BOM Items) or choose the icon Start of the navigation pathMore Next navigation step  Add BOM ItemsEnd of the navigation path.
    2. In the Add BOM Items dialog box, select the BOM items and choose Add BOM Items.
      The selected BOM items are added as follows:
      • If you've selected a component, the BOM items are added as Manufacturing-consumable component and the component gets converted into an assembly.

      • If you've selected an assembly, the BOM items are added as manufacturing-consumable components.

      • If you've selected a manufacturing-consumable component, the BOM items are added as a manufacturing-consumable component. The selected manufacturing-consumable component gets converted into a Manufacturing-consumable assembly.

  6. To edit the BOM item attributes of the selected component, choose (Details) in the Target panel.

    You can update the following attributes of the BOM item:

    Details Attributes

    BOM Component Details

    You can edit the attributes in the following sections:
    • Basic Details

    • Text Details

      Item Text 1 and Item Text 2

    Variable-Size Item Details

    Size 1, Size 2, Size 3, Size Unit, Formula Key, Number of Variable-Size Item, Quantity of Variable-Size Item, Quantity Unit

    Text Details

    Item Text 1 and Item Text 2

    Production Properties

    Consists of additional attributes relevant for production BOM.

    Administrative Details

    None

    Object Dependencies

    ID, Description and Select Condition.

  7. To remove any components or assemblies from the target MBOM structure, choose (Remove nodes from target) or choose the icon Start of the navigation pathMore Next navigation step  RemoveEnd of the navigation path.
  8. [Optional] To maintain routing, choose Routing mode from the right-hand corner of the screen. For more information, see Assigning Routing.
  9. After you’ve finished making changes to the target MBOM structure, choose Unlock .
  10. When you've completed building the MBOM structure and are ready to publish it to the ERP system (SAP S/4HANA Cloud Private Edition, SAP S/4HANA, SAP S/4HANA Cloud Public Edition, or SAP ERP), choose Publish to ERP System.
  11. [Optional] To freeze the target MBOM in the current handover activity from any further changes, choose Release.
    1. Choose Create Baselines to create a baseline for the target MBOM. If a routing is linked to the target BOM, it will also be associated with the baseline object, depending on the configuration profile used. See How to Create Baseline in the Handover Process (Target MBOM).

Results

Once published, an alternative manufacturing bill of material is created in the external source system (SAP S/4HANA Cloud Private Edition, SAP S/4HANA, SAP S/4HANA Cloud Public Edition, or SAP ERP). The handover status changes to Published.