Switching Resources

Use

You can re-assign a task or group of tasks that are assigned to a deactivated resource by switching resources from the Alert Monitor.

Note Note

You can also switch resources from a presentation device. For more information, see Switching Resources in Using a Resource.

End of the note.

Prerequisites

  1. The tasks for which you want to switch resources have been confirmed at source but not at destination.

    In the case of a task bundle, at least one of the tasks has been confirmed at source but not at destination.

  2. The resource to which you want to switch (the active resource) is qualified to perform the tasks.

Procedure

  1. From the hierarchy tree, display the Deactivated Resources alerts located under Resource.

  2. From the ALV, select the row corresponding to the deactivated resource from which you want to switch.

  3. From the ALV tool bar, choose .

  4. Choose Switch from the pop-up menu.

    The Switch Resource dialog box appears, displaying the following:

    • In the top half, a list of the tasks assigned to the resource

    • In the bottom half, a list of suitably qualified resources to which you are able to switch

  5. Select the row corresponding to the resource to which you want to switch.

  6. If there are no suitably qualified resources to which you can switch, choose Force Confirm.

    For more information on force confirmation, see Force Confirming Tasks.

    Note Note

    The Force Confirm pushbutton is not displayed when there are suitably qualified resources.

    End of the note.
  7. Save.

    The Switch Resource dialog box disappears.

Result

The tasks are now assigned to the active resource, which can access them by choosing Start of the navigation path Switch Next navigation step Get switched tasks End of the navigation path from the main menu of its presentation device.