Total Schedule and Lead Time Deviation: Order View
Technical Name: 0PP_C01_Q007
Use
This query compares schedule deviations of order release, start and delivery dates and determines which caused the greatest lead time deviation. It also provides information on how well production is being planned.
Free Characteristics
InfoObject |
Description |
0PRODORDER__0MRP_CONTRL |
MRP controller, variable &0S_PDISP& |
0MATERIAL |
Material, variable &0S_MAT& |
0PRODORDER |
Order |
0CALMONTH |
CalYear/Month, variable &0I_CALMO& |
0CALDAY |
Calendar day |
Rows
InfoObject |
Description of InfoObject (or Restriction or Calculation Formula) |
0PLANT |
Plant, variable &0S_PLANT& |
Columns
InfoObject |
Description of InfoObject (or Restriction or Calculation Formula) |
| 0C_PTA_STARTDEV |
Total deviation start |
| 0C_PTA_DELDEV |
Total deviation delivery date |
| 0C_TA_LEADTIMEDEV |
T/A deviation lead time |
| 0C_T_LEADTIME |
Target lead time |
| 0C_A_LEADTIME |
Actual lead time |
| 0C_PTA_RELDEV |
Total deviation release |