Technical Name: 0C_T_LEADTIME
Use
Planned/Actual Comparison: Order/Material View:
This InfoObject calculates the average, target lead time per production order.The actual lead time is calculated in days and is made up from the difference in time between the target start date and the target finish date.
Technical Data
|
Available from Release |
R/3 Release 3.0F |
|
Calculation |
‘ Tgt Lead Time’ / 'Num.ProdOrd.' |