Start of Content Area

InfoCube documentationPlan/Actual Comparison Material Consumption  Locate the document in its SAP Library structure

Technical name: 0PP_C05

Use

This InfoCube contains all the material consumptions of the production process uploaded from the source system(s). The data is mapped for the actual release date to enable a plan/actual comparison. In addition, data is not stored until a goods issue, a confirmation or a goods receipt for a manufacturing order is posted.

You can find more information in Special Features When Using PP-PI.

Note

An aggregate is provided in the Standard System for this InfoCube via the following characteristics: Plant/Material/Component/Month.

InfoSources

2LIS_04_S282: Order Component, BW (up to R/3 Release 4.0A)

2LIS_04_P_COMP: Material view from PP/PP-PI (from R/3 Release 4.0B)

Characteristics

InfoObject

Description

0COMPONENT

BOM components

0DOC_NUMBER

Sales document

0MATERIAL

Material number

0PLANT

Plant

0PRODORDER

Manufacturing order

0P_PLANT

Planning plant

Time Characteristics

InfoObject

Description

0CALYEAR

Calendar year

0CALDAY

Calendar day

0CALMONTH

Calendar year/month

0CALQUARTER

Calendar year/quarter

0CALWEEK

Calendar year/week

0CALDAY – Calendar day is filled in the update rules using the actual release date. The other time characteristics are determined using an automatic time conversion.

Key Figures

InfoObject

Description

0REQMTSQTY

Target quantity components (requirements quantity)

0WITHDRWQTY

Actual quantity components

0WITHDRWVAL

Actual value components

0TGTCONSQTY

Target quantity components, according to actual quantity GR

Units

InfoObject

Description

0BASE_UOM

Base unit of measure

0CURRENCY

Currency key