You use this function if you want to change the deadlines for a work item at workflow runtime. This dialog box displays all the deadlines of work item processing.
For more information, see Current Deadlines of a Work Item.
Depending on whether the work item represents a step in the workflow or a single-step task, the deadlines were either specified when this step was defined in the workflow definition or when the single-step task was started in dialog.
The dialog box is split into the following sections:
Deadlines
Start by (latest start)
End by (duration)
Plan dates
Start by (requested start)
End by (required end deadline)
A monitored deadline shown with blue is in the past. If
is also displayed, the appropriate action has been initiated (for example, the deadline recipient has been informed).
Actual dates/times
Created on: Creation date/time of the work item
(Technically: The work item is created with the status ready or - if the requested start date has not yet been reached - with the status waiting).
Processed from: Start of processing
(Technically: Transition of the work item to the status in process).
Completed on: End of processing or date when set to "done"
(Technically: Transition of the work item to the status completed).
To execute this function, choose
in the
work item display.