Details of Analysis 
The analysis lists in the Solution Documentation Assistant include detailed information about systems, time periods, and general analysis settings. This detailed information is in the Analysis Projects Overview, the Analyses Overview, and the Analysis Results Overview.
The detailed information tells your the exact analysis settings, which you can then adjust for a new analysis.
You have called one of the following views in the Solution Documentation Assistant:
You have selected an analysis in the analyses table.
Or you have called the Analysis Results View and selected the Analysis Settings tab.
You find the detailed information in the Details of Analysis '<name of analysis>' area on the following tabs:
Systems shows a table of the logical components and their systems and clients.
Note
All logical components which were used in the underlying analysis project when the analysis was created, are shown.
The following are displayed for each analysis:
Name of the Logical Component. The name is copied from the underlying Solution Manager project.
System. The system was defined when the analysis was created.
Installation number of the system
Client specified when the analysis was created
RFC destination. The target address of the specified system is, for example, required to be able to include customer objects in the analysis using RFC.
Workload. The checkbox shows whether check steps of the transaction and report type are included in the analysis.
SQL. The checkbox shows whether the analysis includes SQL check steps.
Note
To include SQL check steps, you have to specify the corresponding RFC destination.
BAdI. The checkbox shows whether the analysis includes check steps for Business Add-Ins (BAdIs).
Periods specified when Creating the Analysis. These time periods are complete months for which you can expect analysis data from the specified systems.
Note
The planned start of the analysis is relevant for the time period. For an immediate start, the current month is never available for analysis, only completed months.
For a planned start in the future, the month in which the analysis is started is not available for analysis either. However, months that are still in the future at the time of analysis creation might be available.
SQL Scheduling for managed systems specified when Creating the Analysis. These periods are specified for every single managed system that was selected for executing SQL check steps.
Note
In creating an analysis that includes SQL check steps, the start and end time as well as the maximum number of work processes to be used (as an absolute figure or percentage portion) are specified.
When the analysis is performed, the currently available resources are always taken into account. If the specified period is exceeded for a system, the analysis for this system is terminated so that the resources can be released.
Global Settings made when Creating the Analysis.
Include high system-load-inducing SQL statements
Get All Customer Objects
Task Types, for example, dialog, background, and spool.