Campaign Functions in the Campaign
Transaction
In the campaign transactions, you can display all production campaigns for a planning version and its orders in a table. In the processing view, you can do the following:
● Create campaigns
● Add orders to campaigns
● Remove orders from campaigns
● Split or merge campaigns
● Move orders from one campaign to another
You can plan campaigns in the Detailed Scheduling
Planning Board. For more information, see Campaign Functions in
the DS Planning Board.
·
Adding orders to
campaigns
If you want to add orders to
a campaign, those are in-house production
orders.
·
Removing orders
from campaigns and dissolving campaigns
Customizing settings determine whether you can remove an order from a campaign
or dissolve a campaign.
You can make these settings in Customizing for Production Planning and
Detailed Scheduling. Choose Global Settings
→ Maintain Global
Parameters and Defaults.
For more information, see Campaign Statuses
and Campaign
Integration Between SAP APO and SAP R/3.
The left section of the Production Campaign screen displays a list of the campaigns for the planning version. By double-clicking a campaign, you can display the header information and the orders that belong to the campaign in the right section of the screen.
The following functions are available:
Function |
Use |
|
When you choose this function, the system creates an empty campaign. When you choose
You can also use this function by choosing Production Campaign → Create. |
|
When you choose this function, the system creates new orders for the products you specified and adds them to the selected campaign. A dialog box appears in which you specify the following: ● Products ● Location ● Planned Quantity ● Start Date ● End Date The system uses the PP strategy instead of the DS strategy for this function.
If the campaign condition must be considered, the system may not be able to add orders to a campaign without violating the condition. In this case, the system terminates the function. |
|
When you choose this function, the system displays a list of existing orders for the product, and you can select orders to add them to the campaign. A dialog box appears in which you specify a product. You can move an order from one campaign to another. If you do this, the order may be rescheduled. If not done in alignment with the scheduling profile, the movement may be disallowed.
· If the campaign requirements must be considered, the system may not be able to create a campaign without violating the requirements. In this case, the system terminates the function. ·
You can use the
/SAPAPO/PCM05_ADDPOS Business
Add-In (BAdI) to execute user-specific checks to decide whether an
in-house production order can be added to a campaign. |
|
When you choose this function, the system removes the selected orders from the campaign. Even though the orders are not associated with the campaign, they still exist in the system. |
|
When you choose this function, orders that appear after the selected order are assigned to the new campaign. |
|
To merge two or
more campaigns, select the target campaign into which you wish to merge the
other campaign, and choose Campaigns across resources can be merged. |
|
If campaigns with
errors are created during planning, the system issues alerts. Once campaign
alerts exist, the Campaign Alerts tab and the To eliminate the
alerts, choose |
|
To position an
order at the beginning of the campaign, select the order and choose You can only position one order at the beginning. |
|
To undo the
positioning of an order, select the order and choose |
|
To position an
order at the end of the campaign, select the order and choose You can only position one order at the end. |
Convert
Campaign |
To convert the
planned orders of a campaign to process orders, select a campaign and choose
Edit → Convert Production Campaign. |
Dissolve Campaign
|
To remove all orders in a campaign and delete the campaign’s header data, select a campaign and choose Edit → Dissolve. Even though the orders were removed from the campaign, they still exist in the system. |
...
1.
On the
SAP Easy Access screen, choose Advanced
Planning and Optimization → Production Planning
→ Interactive Production
Planning → Production
Campaign.
The Production
Campaign screen appears.
2.
Enter the planning
version and choose
.
The Change Production Campaign screen appears.
On this screen, you can access
the above-mentioned functions.