Prioritized Materials Planning: Batch Control Prioritization of requirements results in purchase requisitions with different classifications in the system. You can continue processing these purchase requisitions systematically using batch control.
Alternatively, you can continue processing using user control .
You have made the required settings in Customizing for
Defense Forces and Public Security
by choosing
.
In the case of batch processing, the system carries out the following actions in accordance with the settings made in Customizing:
It carries out an availability check, if required by the document type.
It can change the supplier in order to trigger the requirement to be forwarded.
It can trigger the requirement to be forwarded to the next logistics level.
It can create deliveries.
You can carry out the process with or without workflow control .
Start the application
Background Processing of Prioritized Materials Planning
(transaction
/ISDFPS/PRPLB
).
The selection screen of the same name appears.
Make the required selection settings.
If you set the
High-Priority Requirements
indicator, the system selects all the purchase requisitions with the requirement priorities defined in Customizing. This results in the following:
If you are working with the release procedure for purchase requisitions, the system takes into account only released open purchase requisitions. See also Customizing for
Materials Management
under
. Otherwise, the system selects all open purchase requisitions.
The system does not select any reservations.
The system does not carry out rescheduling.
In the
Reqmt Priority
fields, you can specify a
subset of the value range defined in Customizing.
If you make entries in the
Advice Code
fields, the system processes only the purchase requisitions that contain the specified advice codes.
Choose
Execute.
The system starts processing the purchase requisitions in accordance with the settings made in Customizing.