Single Activity and Multiactivity Resource Only one activity can be carried out at a time in a single-activity resource.
Several activitiescan be carried out at once in a multiactivity resource.
You can carry out to-the-second planning for both resource types in Production Planning and Detailed Scheduling (PP/DS) and Capable-to-Match Planning (CTM) to determine exact production dates. You can also define planning parameters that allow you to carry out a bucket-oriented capacity check in the CTP process and in block planning.
Single and multiactivity resources have the following capacity categories:
Time-Continuous Capacity
The system can plan orders to the second using the time-continuous capacity . The system determines the available capacity of the time-continuous capacity from the working time data.
PP/DS Bucket Capacity
The system uses the PP/DS bucket capacity to carry out a bucket-oriented capacity check in the CTP process and in block planning. You can use this procedure to check the capacity availability for incoming sales orders and reserve the required capacity.
The system determines the available capacity of the PP/DS bucket capacity from the productive time of the time-continuous capacities and the parameters that you have defined on the PP/DS bucket capacity tab page. If you wish to use block planning with the bucket-oriented capacity check, then you must define that the system uses the available capacity of the PP/DS bucket from block planning.
The following working time data must be maintained for single-activity and multiactivity resources. This data is used by the system for scheduling activities:
Detailed working and break times
Rate of resource utilization
The rate of resource utilization is used to estimate the average periods when the resource is unavailable (due to technical and organizational failures) during working times. The rate of resource utilization is defined as the percentage relationship between the productive time and the working time that remains once the breaks have been subtracted.
The
productive time
of the resource is relevant for scheduling activities. It is calculated using the following working time data:
Productive time = (work end – work start – break duration) x rate of resource utilization / 100%
Productive time is the time that is actually available for carrying out an activity during working time. You should define the activity duration in the production process model (PPM) for cases in which the resource is available without interruption and with 100% rate of resource utilization. During scheduling, the system determines the actual duration of the activity. This is dependent on the productive time for the resource.
A single-activity resource upon which only one activity can be executed at a time has a dimension-free capacity of
one
. For single-activity resources the capacity value is fixed in the system. A single-activity resource can only have two different situations: Either it is loaded with an activity or it is not loaded at all. As a result, only the working time data, in other words the “time capacity” is relevant for scheduling activities on such a resource.
Multiactivity resources are used to map resources on which several activities can be carried out at a time. The maximum number of activities that can be scheduled at the same time depends on the organizational or technical conditions for the resource. In order to model the multiple loading on the resource, you define a multiactivity resource in addition to the working time data (“time capacity”), a capacity that reflects the technical and organizational requirements on the resource:
If the multiactivity resource is, for example, a turnery with five lathes, you can schedule up to five parallel turning activities on the resource. The turnery has a dimension-free capacity of
five
.
Another example of a multiactivity resource is a saw that can cut a slab/block up to three meters long into pieces. This block can also be formed from a combination of several individual blocks of different lengths. These individual blocks can also come from different orders. You can schedule as many activities on this resource at the same time as long as the total length of the individual blocks does not exceed three meters. The saw has the capacity
three meters
.
Each activity that is executed on the multiactivity resource “consumes” a certain proportion of this capacity. You can only schedule as many activities at the same time as the available capacity allows for.
You define the resource consumption of an activity in the PPM. The resource consumption is the proportion of the multiactivity resource capacity that the activity consumes.
Within a resource you can define various capacity variants with different working time data and capacities and select the variant of the resource to be used for planning. See Capacity Variants for more information.