 PP/DS Bucket Capacity

Use

You define the parameters for the PP/DS bucket capacityon this tab page. You use the PP/DS bucket capacity to carry out a bucket-oriented capacity check in the CTP process and in block planning. You use the bucket-oriented capacity check when the available capacity for resources becomes critical.

Integration

You can also maintain the parameters for the PP/DS bucket capacity in the R/3 system for the APO data of the scheduling-relevant capacity for the work center. You then transfer the work center to the SAP APO system using the APO Core Interface .

Prerequisites

  • You can only create the parameters for the PP/DS bucket capacity for the following resource types:

    • Single-Activity Resource

    • Single-Mixed Resources

    • Multi-activity resource (no dimensions)

    • Multimixed Resources (no dimensions)

  • You have set the Finite Planning indicator on the General Data tab page.

  • You have define the parameters for the time-continuous capacity .

Features

You create PP/DS buckets by defining the parameters for the PP/DS bucket capacity on the PP/DS Bucket Cap. tab page for the resource and then saving your entries.

Bucket Definition

For the CTP check, choose the setting From Time-Continuous Capacity in the Bucket Definition field. The system derives the available capacity of the PP/DS bucket from the available capacity of the time-continuous capacity of the resource.

For block planning, choose the setting From Block Planning in the Bucket Definition field. The system derives the available capacity of the PP/DS bucket from the available capacity of the blocks. As long as you have not defined any blocks, the system will continue to derive the available capacity from the time-continuous available capacity.

Bucket Schema

You can define the size and start time of a PP/DS bucket in the Bucket Schema field. The scope of a bucket is determined by the period that you define. If, for example, you define the bucket scheme Day , then the available capacity of a bucket is one day. If, for example, you define Week , then the available bucket capacity is one week. The individual buckets always have the same duration.

If you require user-defined periods, then you can change the predefined periods using BAdI /SAPAPO/CRESBUCKET.

Example Example

For example, enter the period Day in resource maintenance. The duration of the bucket is then one day. You can use the BAdI to change the predefined bucket by combining two days for a bucket, for example.

End of the example.

A suitable bucket size depends on the following factors:

  • Average order size

    The bucket duration should be long enough for an operation of a large planned order to be produced within a bucket. Alternatively, you can define settings for the maximum lot size in the product master that allow all operations to be produced within a bucket.

  • Required information quality

    The quality of information is inversely proportional to the bucket size. This means that the quality of information becomes worse when the bucket duration increases. For example, the quality of information is very bad if a sales order with a processing duration of one day is contained in a bucket with a duration of one year.

Bucket Factor in %

The bucket fact is used to determine the relationship between the available capacity of the time-continuous capacity and the bucket capacity.

The bucket factor is used to determine the capacity reduction for the bucket capacity requirement of the sequence-dependent setup activity.

Finite Capacity

The Finite Capacity field determines if the bucket or the time-continuous capacity of a resource is scheduled finitely. The settings for the finite capacity in the strategy profile override the settings for the resource.

Activities

  • The system calculates the available capacity of a PP/DS bucket based on the parameters you defined for the PP/DS bucket capacity according to the following formulas:

    Bucket capacity of single-activity resource = Productive time of resource x Bucket factor

    Bucket capacity of multiactivity resource = Productive time of resource x Number of capacities x Bucket factor

  • You can display the available bucket capacity by choosing the Bucket Capacity function key. The system creates a list that displays the available capacity for each bucket in hours.

  • You can check the PPM/PDS for the resource by choosing the Check Plans function key. The resource must be used as a primary resource in the PPM/PDS and the Calendar Resource indicator must be set. After the PPM/PDS check has been carried out, the system outputs a list of plans in which the resource is used as a secondary resource and/or for which the Calendar Resource indicator is not set.

Example

The maximum time-continuous available capacity for a resource is 22 hours per day. Enter 90% as the bucket factor . You have entered Day (Start: 00:00) as the bucket schema . The system now calculates the available capacity of the PP/DS bucket according to the following formula:

Time-continuous available capacity per day x Bucket factor = 22h X 0.90 = 19.8 h

The available capacity of a PP/DS bucket is 19.8 hours.