Check Confirm 
You can use the CHECKCONFIRM_COMP hook point activity to validate that Kit components for an SFC number have been confirmed at an operation on a Production routing (see Kit).
This activity is commonly used with the PRE_START, PRE_COMPLETE, and POST_COMPLETE hook points.
If this activity is executed at PRE_START, it checks for components at the previous operations only. If this activity is executed at PRE_COMPLETE or POST_COMPLETE, it checks for components at the current operation and all previous operations.
The following table describes rules and settings that you can change for this activity in Activity Maintenance:
Rule |
Setting |
|---|---|
CHECK_ALL_COMP_LAST_OPER |
Determines whether this activity looks for all unconfirmed components, regardless of the operation, only if the SFC number is at the last operation on a Production routing TRUE (default): Checks for all unconfirmed Kit components regardless of whether a Confirm operation is on a Production routing FALSE: Checks only for unconfirmed Kit components on Confirm operations on a Production routing |