 Project System Integration (Network) Locate this document in the navigation structure

Purpose

Integration between the Project System (PS) and Funds Management (FM) components enables you to monitor budget-relevant network processes.

If you are using integration between the Materials Management (MM) component and FM, this is particularly relevant to external procurement transactions and withdrawals from your own warehouse.

If you are using integration between Controlling (CO) and FM and FM-CO posting integration is active, CO transaction completion confirmation and settlement transactions also have an effect on FM.

The link between the network process and FM is established by entering an FM account assignment when you create a network. This means that the system automatically takes this account assignment from the network during subsequent processes triggered automatically by the network, such as purchase requisitions.

The assignment of the FM account assignment is entered on header level for header-assigned networks and is therefore valid for all network transactions; you have to maintain the assignment of each transaction for activity assigned networks.

You have to enter the FM account assignment manually. However, if you have maintained the relevant assignments of FM account assignment elements to Controlling objects in one of the derivation steps of your derivation strategy, the system can derive the FM account assignment from the network account assignment data, for example, from the WBS element to which the network is assigned. The FM account assignment determined with the derivation strategy then appears as a default value that cannot be overwritten.

Note Note

You can implement an alternative proposal logic for the activity assigned network plans using enhancement SAPFMNV, (development class FMFS_E, component EXIT_SAPLFRC4_003); and for header-assigned network plans using enhancement SAPFMNP (development class FMFS_E, component EXIT_SAPLFRC4_004).

End of the note.

Prerequisites

  • Field control

The fields for the FM account assignment elements only accept input in the network/network activity, if their field status is set as optional or required entry. You make the necessary settings in Customizing for Funds Management Government by choosing   Actual/commitments update   /   Integration   Integration   Maintain field status for assigning FM account assignments.  

  • Automatic derivation of FM account assignment in follow-on documents of the network

To allow the FM account assignment to be derived automatically in the follow-on documents in the network, you must copy to your derivation strategy the Network header assignment (Table FMZUOB) derivation step, which is provided by SAP. You make this settings in the Customizing of Funds Management Government by choosing   Master Data   Assignments to Account Assignments from Other Components   Choose   Derivation Rules   .

For further information, see the documentation for the Choose Derivation Rules IMG activity.

  • Derivation of funds center and fund from Controlling object

If you want to derive FM account assignment elements from Controlling objects, you must have defined a rule in your derivation strategy, in which the funds center and fund are assigned to the Controlling objects.

For more information on this topic, see Deriving FM Account Assignment Elements from CO Account Assignments .

  • Derivation of commitment items

SAP recommends that you derive commitment items from the G/L account or the cost element. You must also have defined an appropriate step in your derivation strategy for this derivation.

For more information on the derivation of commitment items from the G/L account, see Deriving Commitment Items from G/L Account .

  • Order completion confirmation and settlement

If you want to integrate the order completion confirmation (activity allocation) and settlement transactions with FM, you must activate them in the Funds Management Government IMG by choosing   Actuals and Commitments Update   Integration   Integration with Cost and Project Controlling   Choose Business Transactions for Integration   .  

  • Actuals activity allocation (RKL)

  • Order settlement (KOAO)

Process Flow

  1. Creating the network/network activity

  2. If the system can determine an FM account assignment from the derivation strategy, it will appear as the default value.

    If the system cannot determine an FM account assignment, you must enter one by choosing   Assignments   Funds management   .

    The FM account assignment elements that you must enter depend on the field control. SAP recommends that you set field control in such a way that you must enter the funds center and, if necessary, the fund. In follow-on postings, the commitment item should be derived automatically from either the G/L account or the cost element. If the commitment item is derived from the cost element, this should ensure that the same commitment item is assigned to the primary cost elements and to the settlement cost elements.

    As long as the FM account assignment in a network/network activity is not complete according to the field control, the order status HMKU (FM account assignment incomplete) is active. This status prevents automatic generation of purchase requisitions for components and services procured externally as well as releasing the order.

  3. Processing the network

  4. Procurement

    If the system automatically triggers purchase requisitions, material reservations, or goods issues by means of the network, the FM account assignment from the network is automatically transferred for these business transactions. You cannot then change the FM account assignment manually in these documents.

    Completion confirmation

    With the completion confirmation, the system transfers the FM account assignment from the network/network activity for the debit posting.

  5. Network settlement

With settlement, the system uses the FM account assignment from the network for the credit posting.