Procedure documentation Display Critical Path as List  Locate the document in its SAP Library structure

Procedure

...

       1.      Execute the Heuristic for Calculating the Critical Path (SAP_PMAN_001), in the detailed scheduling planning board, for example. 

       2.      Define a corresponding heuristic profile in the user profile, and under Settings Heuristics define that the critical path should be displayed as a list.

       3.      To execute the heuristic, choose Functions Heuristics.

The system displays a window that contains a list of all the operations in a network and specifies the (time) delay of the network. The critical operations are highlighted.

The (time) delay is a guideline that indicates by how much (in total) you must reduce planning-related minimum intervals or planning-related offsets so that the network no longer lies in the past.

To reduce the period by which the network extends into the past, you can reduce planning-related minimum intervals between operations and planning-related offsets at requirements along the critical path.

       4.      Choose This graphic is explained in the accompanying text Change, to access the function for maintaining planning-related minimum intervals and planning-related minimum offsets.

See Processing of Planning-Related Minimum Intervals and Planning-Related Offsets

 

 

 