Display Critical Path as List
...
1. Execute the Heuristic for Calculating the Critical Path (SAP_PMAN_001), in the detailed scheduling planning board, for example.
2. Define a corresponding heuristic profile in the user profile, and under Settings → Heuristics define that the critical path should be displayed as a list.
3. To execute the heuristic, choose Functions → Heuristics.
The system displays a window that contains a list of all the operations in a network and specifies the (time) delay of the network. The critical operations are highlighted.
The (time) delay is a guideline that indicates by how much (in total) you must reduce planning-related minimum intervals or planning-related offsets so that the network no longer lies in the past.
To reduce the period by which the network extends into the past, you can reduce planning-related minimum intervals between operations and planning-related offsets at requirements along the critical path.
4.
Choose
Change, to access the function for
maintaining planning-related minimum intervals and planning-related minimum
offsets.
See Processing of Planning-Related Minimum Intervals and Planning-Related Offsets