Some of the key figures available in Cost Object Controlling
are listed below. Note that the availability of key figures depends on the application component and the objects used in the application component. For example, you can analyze the planned costs for production orders (in Product Cost by Order
) and sales orders (in Product Cost by Sales Order
), but not for product cost collectors (in Product Cost by Period
).
You can display key figures:
Using cost analysis
For the cost element itemization for material cost estimates and sales order cost estimates
For all summarization hierarchies (including order hierarchies with classification)
For reports for cost object hierarchies
Using product drilldown
Using special reports
In the report categories Object Lists, Object Comparisons, and More Reports
See the following sections for information on the key figures available for each application component:
If you are using cost analysis reports, it is recommended that you read these sections, because in this case the individual reports are not explicitly described.
Cost analysis reports use the functionality of the ABAP List Viewer while offering additional functions in cost analysis. You can define layouts in cost analysis containing the key figures that you want to analyze. The column selection for the layouts contains different field groups (column lists) that separate the key figures into logical groups.
For general information on working with layouts, see the following:
For general information on grouping information in layouts, see Creating Subtotals
See the following text for detailed information on the most important key figures:
You can display planned costs for the following objects in the information system of Cost Object Controlling as long as the planned costs have been updated to the object.
Production orders, process orders (if the costs were updated to the manufacturing order and not to a product cost collector)
CO production orders
Sales order items
Planned costs are only updated to a sales order item if the sales order item carries costs and revenues. You can also create a sales order cost estimate if the sales order item does not carry costs and revenues. A sales order cost estimate can also be analyzed if no planned costs are updated.
In Product Cost by Sales Order
, a differentiation is made between the planned costs that were planned directly on the sales order cost estimate and the planned costs on the assigned objects.
An additional view is available with a planned cost report for a sales order that displays the planned costs for the sales order item and for the assigned objects (manufacturing orders).
Internal orders
General cost objects
No planned costs are updated for product cost collectors. You analyze the results of the preliminary cost estimates of product cost collectors in the information system of Product Cost Planning
in the same way as you do with other material cost estimates with quantity structure.
Calculation of Planned Values in Product Cost by Sales Order
CO Internal Orders
Both the true actual costs and statistical actual costs are displayed in the Actual
column in reports for the sales order item. The true actual costs can be differentiated from the statistical actual costs through the cost element. The Funds Commitment in Inventory
layout makes it possible to report true actual costs separately form statistical actual costs.
Work in process can be calculated for the following objects:
Product cost collectors
Work in process for product cost collectors is always calculated at target costs.
Production orders and process orders
As a rule, manufacturing orders are settled cumulatively (settlement type FUL (full)). In this case, work in process is calculated at actual cost. If manufacturing orders are settled by period (settlement type PER), work in process is calculated at target cost.
Note
Summarized Analysis with Product Drilldown
Work in process is derived from the results analysis cost elements for both objects with settlement type Periodic
and objects with settlement type Full Settlement
. If the results analysis cost elements are not assigned in the cost component structure for product drilldown, the work in process appears in the cost component Other
(if defined) or as not assigned.
Results analysis data (including work in process) can be displayed separated into creation and usage if the indicator Split creation/usage
is selected in Customizing for the results analysis version. If this indicator is not selected, the system displays the balance. Check this Customizing setting in the implementation guide of the respective application component of Product Cost Controlling
under . The screen Change View Results Analysis Versions: Overview
appears. Select the line to display the screen: Display Results Analysis Versions: Detail
.
Creation and usage are not separated here. For the work in process, the report also shows the actual debits, the actual credits, and the balance.
Make sure that you have calculated work in process in period-end closing in the respective results analysis version.
Note
Reserves for Unrealized Costs
Reserves for unrealized costs only exist for work in process at actual cost.
Results analysis data (reserves for unrealized costs) can be displayed separately according to creation and usage if the indicator Split creation/usage
is selected in Customizing for the results analysis version. If this indicator is not selected, the system displays the balance.
Check this Customizing setting in the implementation guide of the respective application component of Product Cost Controlling
under . The screenChange View Results Analysis Versions: Overview
appears. Select the line to display the screen:Display Results Analysis Versions: Detail
.
Reserves for unrealized costs are only created if the value of the credit associated with the order delivery exceeds the value of the debits. In a particular period the object has either WIP
or reserves for unrealized costs
. This does not apply to summarization objects. With summarization objects, both work in process (at actual costs) and reserves for unrealized costs can exist within a period.
You must have performed results analysis in period-end closing in the respective results analysis version.
The key figures can be displayed and analyzed in detailed reports for individual objects as well as summarized.
Note
Summarized Analysis with Product Drilldown
In summarized analysis with product drilldown, creation and usage are not separated, and reserves are not displayed. You must have calculated work in process in period-end closing in the respective results analysis version.
Work in process, including goods in transport and goods at construction site, can also be calculated with results analysis for the sales order item or internal order.
Results analysis data (including work in process) can be displayed separated into creation and usage if the indicator Split creation/usage
is selected in Customizing for the results analysis version. If this indicator is not selected, the system displays the balance.
You must have performed results analysis in period-end closing in the respective results analysis version. The key figures can be displayed and analyzed in detailed reports for individual objects as well as summarized.
In results analysis for sales order items or internal orders, a variety of results analysis data can be calculated. You can find more information on results analysis data in the following sections:
You can display the following variances:
Plan/actual variances
Plan/actual variances can be displayed for all objects for which plan and actual values were updated. A variance is the difference between planned and actual cost.
Caution
Plan/actual variances can be displayed for sales order items and for production orders and process orders. They cannot be displayed for product cost collectors, because no planned costs are updated on product cost collectors. Instead, you can use the report Material vs. Order
in the report category Object Comparisons
for comparisons between Actual Costs of Product Cost Collectors
and Preliminary Cost Estimates of Product Cost Collectors
.
Target/actual variances
Target/actual variances can be calculated for product cost collectors and manufacturing orders.
Caution
Planned values are adjusted to a reference base in order to calculate variances between target costs and actual costs. This adjustment is performed during the variance calculation process. You calculate variances in period-end closing of Product Cost by Period
and Product Cost by Order
. During variance calculation, the variances to be analyzed are distributed to individual variance categories. These variance categories can be displayed in the information system.
If variances have not yet been calculated, target costs can be calculated dynamically in the information system. The target costs are calculated on the basis of a target cost version.
Note
The target credit in the report is calculated by multiplying the actual quantity by the standard price (with standard price control).
A target credit, however, is only displayed if the comparison object used for calculating target costs is a cost estimate that is independent of an order. Therefore, no target credit record is displayed in a report for target version 1. In the SAP standard system, target costs calculated using the planned costs for an order would be compared with the actual costs (or the net actual costs). Likewise, no target credit record is generated if the target costs were calculated by the report itself rather than during period-end closing.
Target cost calculation is initiated dynamically
No variances are calculated (no variance categories that can be settled exist)
No data is updated
This option enables an ad hoc target/actual comparison for a single object.
Target costs according to variance calculation
Variances according to variance calculation
Addendum: Scrap in Product Cost Controlling
Target Cost Versions in Variance Calculation
Variances with a Valuated Sales Order Stock
Variance Calculation: Process Flow
Example for Variance Calculation
In results analysis for sales order items or internal orders, a variety of results analysis data can be calculated.
Results analysis data (including work in process) can be displayed separated into creation and usage if the indicator Split creation/usage
is selected in Customizing for the results analysis version. If this indicator is not selected, the system displays the balance.
You must have performed results analysis in period-end closing in the respective results analysis version.
The key figures can be displayed and analyzed in detailed reports for individual objects as well as summarized.
See the following sections for information on product drilldown reports:
See the following sections for information on object lists:
See the following sections for information on object comparisons:
For detailed information on other reports, see the sections of the documentation relating to the position in the menu structure.