Daily View 
The view provides an overview of resources and their assignments, time allocations and overall availability within the period of one day.
You can enhance or modify the column data you see in the daily view by choosing SAP IMG ® Customer Relationship Management ® Workforce Deployment ® Service Resource Planning ® Basic Settings ® Business Add-Ins (BAdIs) ® Business Add-In: Resource List Display.
See Resource Overview.
You view the resources on a day-by-day basis showing details on either:
· Schedule
· Basic Availability
When viewing schedule details, you see
· Time Type, which is the assignment comprised of the status abbreviation and the identifier of the demand. The demand identifier is a link where you can view the demand header information.
· Duration, which is determined by the Time Type.
Time Type |
Duration |
Assignment |
Duration of the assignment. When a concrete assignment, this is the end time – begin time |
Availability |
Begin time – end time |
When viewing basic availability you see the periods during which the resource is available or not available.
When in the daily view you can:
· Change to a different resource list view.
· Switch to display either schedules or basic availability
· Review resource availability.
· Select next/previous day or go to different days by entering a key date.
· Display the Employee application for an internal resource or the Service Provider application for an external resource
· Display the Resource Header for a new search following a resource search.
· Select one or more resource for further actions (creating assignments for the resources, for example).
· Sort the resource list on all fixed columns.
When the columns for primary and/or alternative service area have more than one value, further details are shown in the tooltip.