!--a11y-->
AFS MRP List 
You use the display of the AFS MRP list to evaluate the result of the latest planning run. AFS has developed its own function for this. This function displays the result of the latest planning run taking the AFS-specific data into account (grid value and categories). The AFS MRP list displays the requirements shortage and stock excess at SKU level with any corresponding MRP-relevant information.
You can select which data should be displayed in the MRP list, so that the AFS-specific data (grid values and categories) is easier and clearer to read (see Single-Item Planning). You can also include or exclude certain MRP statuses as well as certain stock and requirement numbers in the view.
The AFS MRP list contains the following data for each SKU:
● Stock/ requirements category
● Grid values
● Quantity
● Requirements date
● Availability date
● Requirement type, such as planned independent requirement
● Stock type, such as production order
● Requirement number, such as number of the sales order
● Number of the stock element, such as the batch number or the number of the planned order
● Indicator showing whether a certain stock element is fixed
● Item number in the corresponding document
● Storage location for batches
● Number of the exception message
● Additional information, such as the status of the production order or the end of the SKU horizon.
The MRP statuses help you better understand the stock/ requirement situation after the most recent planning run per SKU of the planned AFS material (see Importance of the AFS MRP Status).
The evaluation of the exception messages helps to indicate exceptional situations per SKU, such as the absence of a BOM or routing.
In the AFS MRP list you can also use the function to call the required components (both AFS and SAP standard components) per MRP element of the planned AFS material. That way you can include the consumption of the AFS components at SKU level per MRP element in the evaluation of the latest MRP run.